How Northampton town centre regeneration projects are progressing

West Northamptonshire Council Drawing showing shops around edge with wide paved area and water features. Passers-by walk through, sit or play gamesWest Northamptonshire Council
Artist's impression of how Northampton's market square could look after

In September politicians from the ruling Conservative group on West Northamptonshire Council (WNC) declared a £33m revamp would move Northampton town centre "ahead of the curve".

A scheme to transform Market Square is nearing completion, while a number of projects are set to formally get under way in 2024.

They have been financed through funding streams such as the Towns Fund, Future High Streets Fund, National Lottery Heritage Fund and Levelling Up Fund.

Where do some of the town's high-profile developments stand as we head into 2024?

presentational grey line

Market Square

Kate Bradbrook/BBC Northampton Market SquareKate Bradbrook/BBC
It is hoped the work will be complete by summer 2024

A controversial £8.5m refurbishment of Northampton's Market Square is well under way.

It began in February, despite a 10,000-strong petition and complaints from traders, who were relocated to a car park on Commercial Way on the edge of the town centre.

Plans for the market, which dates back to 1235, include a new water feature, public seating, lighting scheme and "flexible events space".

Work to install 18 steel stalls on the Market Square began earlier in December.

The project is slated for completion in the summer of 2024.

presentational grey line

Greyfriars

More than 2,000 explosives were used to collapse Greyfriars

The site of a bus station once dubbed "the mouth of hell", Greyfriars is approaching a decade of being nothing more than a vacant space.

Greyfriars bus station, which opened in 1976, was demolished in March 2015 and had dominated the town's skyline for nearly 40 years.

Plans for its development were previously approved in 2016, but did not progress.

Google Greyfriars bus station siteGoogle
The site, pictured here in 2018, has been derelict since it was demolished

Earlier in December, a fresh consultation was launched for the land, which WNC described as "the largest brownfield opportunity" in the town.

The authority's "vision" for the derelict site could include homes, community spaces and a new park.

An "online engagement" will be open until 7 January, with residents invited to share their views, before a second stage of consultation will begin.

It remains unknown exactly when the four-acre (1.62 hectare) site will be developed.

presentational grey line

35-45 Abington Street

Former M&S store in Northampton
The former M&S store in Northampton has been unused since it closed in 2018

Plans to replace the empty BHS and Marks & Spencer department stores on Abington Street with flats and smaller retail units were unveiled in 2022.

BHS closed all of its stores in 2016, while the town's M&S was shut in 2018 as part of a savings plan by the retailer.

This summer, WNC agreed to finance an asbestos clearance programme that the buildings will have to undergo before they can be removed and replaced.

Part of a £9.7m Towns Fund grant will be used to pay for the asbestos work.

According to We Are Northampton, work is expected to begin in 2026 and complete in 2032.

West Northamptonshire Council Artist impression the new buildingWest Northamptonshire Council
The new building will be a combination of accommodation and retail, the council said
presentational grey line

Market Walk

Urban Designs An artists impression of Stack development in Northampton Town CentreUrban Designs
Leisure developer Stack wants to turn Market Walk, formerly known as Peacock Place, into a food and entertainment hub

The former Market Walk shopping centre is set to be transformed into an "innovative food hall and leisure space", under plans revealed in August.

The building, previously known as Peacock Place, was last open in 2018, but leisure developer Stack said it wanted to make it a "focal point" for local people and visitors alike.

A £12.2m transformation has been slated for the site, which sits between the Market Square and Abington Street.

WNC said it would provide about £4.2m worth of investment, through the Towns Fund, along with £8m from Stack, which completed its purchase of the shopping centre building on 1 August.

Subject to a planning application being approved, the council hopes work will begin in spring 2024, opening in summer 2025.

presentational grey line

Four Waterside

Howells Artist impression of what the completed project might look likeHowells
West Northamptonshire Council said the development of Four Waterside was expected to start in 2025

Despite houses and a gas tower being demolished in 2013, nothing has been built at Four Waterside.

However, in October, WNC announced that it had agreed a partnership with developer Cityheart to deliver the "transformational" scheme.

It said work would begin in 2025 to build a new hotel, office spaces and "high-quality" homes.

Plans for the 60,000 sq ft (5,575 sq m) site, near the River Nene and St Peter's Way and behind the University of Northampton Innovation Centre, were first submitted in January 2016.

Four Waterside site
The Four Waterside development was meant to open in 2017 but no building work has begun

Four Waterside was due to open in 2017, but discussions between the council and contractor Kier stalled and the council terminated the agreement in April 2019.

Conservative-controlled WNC said a £1.5m grant from the government's Towns Fund and a further £7m from the Northampton Waterside Enterprise Zone would help deliver the project, which it hoped would "contribute to the wider transformation across the town".

Cityheart will need to submit a planning application for the project to the council. It is hoped the work would be completed by summer 2032.

presentational grey line

Old Black Lion

Work to bring the 16th Century Grade II-listed Old Black Lion pub back to its former glory started in March as part of a £3.5m restoration.

The pub on Marefair has been empty since 2018.

The Churches Conservation Trust (CCT), a charity that runs the adjacent 12th Century Grade I-listed St Peter's Church, is overseeing the project.

Alex Davidson/WNC The Old Black LionAlex Davidson/WNC
The pub burnt down in the great Northampton fire of 1675 but was restored as the Old Black Lion in 1720

The CCT also plans to base its national office on the first floor of the refurbished Old Black Lion.

About £2m of funding has come from the National Heritage Lottery Fund.

Money has also been granted by the Towns Fund, WNC, the Architectural Heritage Fund and West Northamptonshire Development Corporation.

The pub burnt down in the great Northampton fire of 1675 but was restored as the Old Black Lion in 1720.

Work is due to be completed by spring 2024.

presentational grey line

Follow East of England news on Facebook, Instagram and X. Got a story? Email [email protected] or WhatsApp 0800 169 1830