Work to repair weather-damaged pier under way

Adur & Worthing Councils Two large diggers on the pebbles on the beach in Worthing. Two workers in orange high-vis outfits are stood next to them, under the pier. Adur & Worthing Councils
Worthing Pier was closed on 10 October after engineers discovered it had been damaged during a storm

Work to repair a pier in West Sussex after it was damaged by severe weather is under way.

Worthing Pier was closed on 10 October after engineers discovered one of the underside supports had been damaged during a storm.

Some businesses based on the pier previously said they were “blindsided” by the temporary closure.

The first of six steel piles designed to support the structure has been was installed during low tide on Wednesday afternoon.

Adur & Worthing Councils said it was "keen to allow residents and visitors back onto the pier to allow the popular businesses to begin trading again" but had to make sure it was "totally safe".

Adur & Worthing Councils Four workers stood on the beach un Worthing, under the pier. They are all wearing orange high-vis outfits. Another man with a high-vis outfit is using a large industrial digger. Adur & Worthing Councils
Interim repairs are being carried out on Worthing Pier during the tidal window

During the first spring low tide of November on Tuesday, contractors were able to safely check the stability of the ground under the pier and began drilling the first two of six holes for the new steel piles.

The first piles were then driven into the seabed until only around a third of each was left above the surface of the beach, the council said.

The authority said it hoped that the remaining four piles will be driven into the seabed in the coming days, so that a supporting structure can be built on top of them.

The new steel support structure is designed to take the weight off damaged piles so that they can then be replaced.

A council spokesperson said: "We will aim to keep disruption to a minimum, but unfortunately there will be some noise during the work, including in the early hours of tomorrow morning.”

The work is expected to last for about one week.

Follow BBC Sussex on Facebook, on X, and on Instagram. Send your story ideas to [email protected] or WhatsApp us on 08081 002250.

Related internet links