'Shocking' pipework issue at already delayed maternity hospital
A new issue with medical gas pipework at Belfast's long-delayed new maternity hospital has emerged, the Health Minister has confirmed.
Mike Nesbitt told the Assembly that the scale of the problem is believed to be limited to an isolated section of the hospital.
The hospital, at the Royal Victoria site in Belfast, is already almost 10 years behind schedule after numerous delays, but it was hoped it would finally open next year.
In recent months it has been revealed that a high presence of a bacteria in its water system could cause more delay.
The Belfast Trust took possession of the five-storey building in March and began a "clinical commissioning phase" - a process of ensuring a safe transition of service to the new site.
On Tuesday, Nesbitt said he had only been made aware of the gas pipework issue that morning.
'Potentially dangerous bacteria'
Nesbitt said he was "deeply dissatisfied" by the emergence of the problem and when he had been informed about it.
The development came during a debate brought by the Democratic Unionist Party (DUP) criticising the delay in opening the site.
DUP MLA Diane Dodds called for an independent inquiry to take place and said figures showed a potentially dangerous bacteria, Pseudomonas aeruginosa, was found in 459 water outlets in the maternity hospital.
'Another totally shocking revelation'
Responding to the motion calling for an independent inquiry, Mr Nesbitt said: “When I went to bed last night I was not in favour of that, not least because the cost and time associated with a further independent inquiry could be in the order of £3m per annum with a significant time impact and no guarantee of improvement and it could potentially stymie progress.
“However, as of eight o’clock this morning I have become aware of another issue.
“I know Mrs Dodds is very well informed on these issues so I challenge her, I give her 24 hours to discover what the latest problem is with the maternity hospital.
“It is another shocking, another totally shocking revelation.”
Nesbitt later returned to the chamber and provided clarity on the issue, ahead of a vote on the DUP motion.
The vote on the motion passed by 61 to nine, with only the Ulster Unionists and People Before Profit voting against it.
Why the delay?
According to an Audit Office report published in February, work on the new maternity building, commenced in November 2017.
It said phase one was on track for completion in August 2020, phase two was expected to be completed in March 2021 and phase three in September 2021.
The Department of Health told auditors that Pseudomonas bacteria was detected in the water system during the commissioning process for Phase One.
The auditors said the hospital was originally expected to be completed by the end of 2015.
The report said: “Whilst the new maternity hospital has been substantively built it is not operational.
"The latest estimated date for completion of the final phase of the maternity hospital is June 2025, almost 10 years late.
"The original cost estimate was £57m, with costs now expected to be £97m.”
The new hospital is expected to have an admission unit, early pregnancy department and an active birthing centre with 10 dedicated rooms for mothers who choose midwifery-led care.
Also included in the development is a new neonatal unit with 45 cots.
A 10-bed ward is also located directly above the theatres to facilitate the care of high risk antenatal and postnatal women.